home Nuclear Attitude, U Rooppur nuclear fuel shipment arrives after Pakistan airspace delay

Rooppur nuclear fuel shipment arrives after Pakistan airspace delay

A shipment of nuclear fuel for the Rooppur Nuclear Power Plant has arrived in Bangladesh from Russia after complications over permission to use Pakistani airspace were resolved.

The consignment arrived at Hazrat Shahjalal International Airport in Dhaka aboard a special cargo aircraft at 11:43pm on Friday (October 2).

A senior official involved with the project confirmed the arrival. The nuclear fuel is scheduled to be transported from the airport to the Rooppur Nuclear Power Plant site on Saturday under tight security and army supervision.

The aircraft had initially been scheduled to arrive in Bangladesh from Russia on Sept 24. However, the flight could not operate as planned after it failed to receive the necessary clearance to use Pakistani airspace.

Science and Technology Minister Faqir Mahbub Anam later said the aircraft had not received permission to use Pakistan’s airspace. The Pakistan High Commission, however, described the matter as technical and procedural.

According to project officials, nuclear fuel is planned to be brought to Bangladesh on nine cargo flights in total — two for the future refuelling of Unit 1 and seven for the initial fuel supply of Unit 2.

Rooppur project director Kabir Hossain earlier said 48 fuel assemblies for the refuelling of Unit 1 would be transported on two flights, while the fuel required for Unit 2 would arrive on seven flights.

Russia’s state nuclear energy corporation Rosatom has said fuel deliveries for Unit 2 will continue from October through December, with the programme expected to be completed by the end of December.

Meanwhile, commissioning work on Unit 1 is continuing. On Sept 30, the unit completed a 16-megapascal high-pressure test of its pressure-operated relief valves.

Project officials have said three more important tests must be completed before Unit 1 reaches the criticality stage. If those tests are completed as planned, electricity generation could begin by the end of the year.

Russia is supplying the nuclear fuel required to operate both units of the Rooppur plant. The consignments will be transported to the project site in phases under prescribed safety and security arrangements.

Source: Banglanews