Denison Mines Corp. (“Denison” or the “Company”) (TSX: DML) (NYSE American: DNN) is pleased to provide a progress update on the In-Situ Recovery (“ISR”) field test activities occurring at Phase 1 of the high-grade Phoenix uranium deposit (“Phoenix”) at the Company’s 90% owned Wheeler River Uranium Project (“Wheeler River” or the “Project”). The Company is also pleased to announce the discovery of additional high-grade uranium mineralization, including 22.0% eU3O8 over 8.6 metres in drill hole GWR-045, located outside of the existing high-grade resource domain associated with Zone A and Phase 1 of the phased mining approach currently planned for PhoenixView PDF

David Bronkhorst, Denison’s VP Operations, commented, “We are pleased to have safely and successfully completed a substantial portion of the planned 2021 ISR field test program – including the installation of the commercial-scale wells in our five-spot test pattern (“Test Pattern”) and nine of eleven planned monitoring wells. Baseline hydrogeologic testing and permeability enhancement efforts completed within the Test Pattern thus far are encouraging and will inform future test work as we progress towards the initiation and completion of a full-scale tracer test during the remainder of the program.  The tracer test is planned to be completed during the third quarter and is expected to provide a more complete understanding of the operating parameters in Phase 1 and important information in support of our objective of permitting and completing a lixiviant test in 2022 – which is considered a key de-risking milestone for the project.

Additionally, the discovery of a thick interval of high-grade uranium mineralization in GWR-045 is quite exciting, as it has the potential to meaningfully increase the high-grade mineral resources estimated within the area currently expected to represent the first phase of ISR mining at Phoenix.”

Interim progress highlights from the 2021 ISR field program include the following:

  • Completed installation of commercial-scale wells: All five new commercial-scale well (“CSW”) installations planned for the Test Pattern, located in the Phase 1 area of Phoenix, are complete. The Test Pattern consists of the newly installed five-spot pattern (GWR-038 to GWR-042), and GWR-032, which was installed in 2019 (see Figure 1). Taken together, the CSWs are spaced between 5 and 30 metres apart and are expected to facilitate further hydrogeologic testing and assessment of down-hole permeability enhancement tools as part of the ongoing field program.
  • Successful installation of monitoring wells: Nine of eleven monitoring wells (“MWs”) have been successfully installed within the Phase 1 area (see Figure 1) and outfitted with the associated materials and monitoring equipment to facilitate ongoing observation of the current and future hydrogeological test work – allowing for detailed hydrogeological assessment and water quality sampling. The final two MWs are expected to be completed in early August.
  • Collected baseline hydrogeologic information and deployed permeability enhancement: The MaxPERF drilling tool was successfully deployed in all planned CSWs to create a series of lateral drill holes (penetration tunnels) designed to mechanically engineer increased access to the existing permeability of the ore zone formation.
  • Discovery of High-Grade Mineralization in GWR-045: GWR-045 was completed as part of the ISR field test program to install MWs to the northwest of the five-spot Test Pattern. Based on the Phoenix block model, GWR-045 was expected to intersect low-grade uranium mineralization along the northwestern margin of the deposit, approximately 5 metres outside of the boundary of the Phoenix Zone A high-grade resource domain. The drill hole, however, intersected a thick interval of high-grade unconformity-associated uranium mineralization grading 22.0% eU3O8 over 8.6 metres (see Figures 1 and 2; Table 1). The high-grade mineralization intersected by GWR-045 remains open to the northwest, representing an area for further exploration and potential mineral resource expansion of Phoenix. Denison’s exploration team is currently incorporating the results of GWR-045 into the Phoenix geological model to evaluate the potential to extend the high-grade domain with additional exploration drilling in the Phase 1 area of Phoenix.

Table 1 – GWR-045 Mineralized Intersection

Drill Hole

From (m)

To (m)

Length (m)4

eU3O8 (%)1,2,3

GWR-045

406.95

415.55

8.6

22.0

Notes:

1. eU3O8 is radiometric equivalent U3O8 derived from a calibrated total gamma down-hole probe.

2. Composited above a cut-off grade of 0.1% eU3O8 

3. Composited using a 1.0 metre minimum mineralization thickness and 1.0 metre maximum waste

4. The stated length is interpreted to represent true thickness as the drill hole is oriented vertically, and the unconformity mineralization is interpreted to lie horizontally

Activities Planned for Remainder of 2021 ISR Field Program

Once the final two MWs are completed, the Test Pattern will be ready for additional hydrogeologic test work, including the following planned activities:

  • Multi-day pump and injection tests to be conducted on the full-scale Test Pattern. These tests are intended to assess the Test Pattern’s total permeability, and support an ongoing assessment of the ability of various permeability enhancement tools to normalize the varying levels of permeability associated with the natural fracture/structure network of the deposit;
  • Ion tracer tests will be conducted by injecting and recovering solution with dissolved inorganic salts throughout the full-scale Test Pattern. This process is expected to (1) establish breakthrough times for each CSW, with injection from the centre well in the Test Pattern and recovery from the outer ring wells, and (2) confirm modelling of sub-surface pathways. Taken together, this test is expected to provide a more complete understanding of the hydrogeologic characteristics expected throughout Phase 1 and the necessary datasets for the design and permitting of a lixiviant test planned to make use of the same Test Pattern in 2022;
  • Deployment and evaluation of additional permeability enhancement techniques based on individual well characteristics and associated hydrogeological assessments; and
  • Extensive collection and analysis of permeameter samples from new and historic drill core for the assessment of matrix permeability spatially distributed throughout the areas representative of all of the mining phases planned for Phoenix.

All test work in 2021 will be conducted using site groundwater. Following the field tests and associated data collection, detailed hydrogeological and geochemical modelling of the test data will be carried out by various Qualified Persons (“QPs”).

COVID-19

The Company is committed to ensuring that the Wheeler River site is a safe operating environment for its staff and contractors and that the Company’s field activities do not compromise the health and safety of the residents of northern Saskatchewan.  In 2020, the Company’s Occupational Health and Safety Committee in Saskatoon developed a comprehensive guide for the safe resumption of work at Wheeler River.  The protocols consider the unique health and safety risks associated with operating a remote work camp amidst the ongoing COVID-19 pandemic.  Public health guidelines and best practices (including testing) have been incorporated into the Company’s protocols.

Despite the Company’s current intentions, it is possible that the 2021 ISR field program may be disrupted by the continuously evolving social and/or economic disruptions associated with the COVID-19 pandemic, which are outside of the control of the Company – for example, provincial or local travel restrictions, or changing public health guidelines, could impact the ability of Company or contractor staff to attend to
the site.

Use of Radiometric Equivalent Grades

The Company typically reports results as preliminary radiometric equivalent grades (“eU3O8”), derived from a calibrated downhole total gamma probe, during active exploration programs and subsequently reports definitive assay grades following sampling and chemical analysis of the mineralized drill core. In the case where core recovery within a mineralized intersection is less than 80%, radiometric grades are considered to be more representative of the mineralized intersection and may be reported in the place of assay grades. Radiometric equivalent probe results are subject to verification procedures by qualified persons employed by Denison prior to disclosure. For further details on the total gamma downhole probe methods employed by Denison, QAQC procedures and data verification procedures please see Denison’s Annual Information Form dated March 26, 2021 available on Denison’s website and under its profile on SEDAR and EDGAR.

About Phoenix Phase 1

Phase 1 of Phoenix is estimated to contain approximately 22.2 million pounds U3O8 (37,242 tonnes at 27.1% U3O8, above a cut-off grade of 0.8% U3O8) in Probable mineral reserves.  Based on current designs, the Company estimates approximately 6.6 million pounds U3O8 (7,717 tonnes at 39.2% U3O8, above a cut-off grade of 0.8% U3O8) in Probable mineral reserves are contained within the expected operating perimeter of the Test Pattern (see Figure 1). These estimates are derived as a direct subset of those reported in the Technical Report titled “Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018 with an effective date of September 24, 2018. The key assumptions, parameters and methods used to estimate the mineral reserves herein remain unchanged.

About Wheeler River

Wheeler River is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, in northern Saskatchewan – including combined Indicated Mineral Resources of 132.1 million pounds U3O8 (1,809,000 tonnes at an average grade of 3.3% U3O8), plus combined Inferred Mineral Resources of 3.0 million pounds U3O8 (82,000 tonnes at an average grade of 1.7% U3O8). The project is host to the high-grade Phoenix and Gryphon uranium deposits, discovered by Denison in 2008 and 2014, respectively, and is a joint venture between Denison (90% and operator) and JCU (Canada) Exploration Company Limited (10%).

A Pre-Feasibility Study (“PFS”) was completed for Wheeler River in late 2018, considering the potential economic merit of developing the Phoenix deposit as an ISR operation and the Gryphon deposit as a conventional underground mining operation.  Taken together, the project is estimated to have mine production of 109.4 million pounds U3O8 over a 14-year mine life, with a base case pre-tax NPV of $1.31 billion (8% discount rate), Internal Rate of Return (“IRR”) of 38.7%, and initial pre-production capital expenditures of $322.5 million. The Phoenix ISR operation is estimated to have a stand-alone base case pre-tax NPV of $930.4 million (8% discount rate), IRR of 43.3%, initial pre-production capital expenditures of $322.5 million, and industry leading average operating costs of US$3.33/lb U3O8.  The PFS is prepared on a project (100% ownership) and pre-tax basis, as each of the partners to the Wheeler River Joint Venture are subject to different tax and other obligations. 

Further details regarding the PFS, including additional scientific and technical information, as well as after-tax results attributable to Denison’s ownership interest, are described in greater detail in the NI 43-101 Technical Report titled “Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018 with an effective date of September 24, 2018.  A copy of this report is available on Denison’s website and under its profile on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml

Denison suspended certain activities at Wheeler River during 2020, including the EA process, which is on the critical path to achieving the project development schedule outlined in the PFS.  While the EA process has resumed, the Company is not currently able to estimate the impact to the project development schedule outlined in the PFS, and users are cautioned against relying on the schedule estimates provided therein, including with respect to the start of pre-production activities in 2021 and first production in 2024.

About Denison

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. In addition to the Wheeler River project, Denison’s interests in the Athabasca Basin include a 22.5% ownership interest in the McClean Lake joint venture (“MLJV”), which includes several uranium deposits and the McClean Lake uranium mill that is contracted to process the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and Midwest A deposits, and a 66.90% interest in the Tthe Heldeth Túé (“THT,” formerly J Zone) and Huskie deposits on the Waterbury Lake property. The Midwest Main, Midwest A, THT and Huskie deposits are located within 20 kilometres of the McClean Lake mill. In addition, Denison has an extensive portfolio of exploration projects covering approximately 280,000 hectares in the Athabasca Basin region.

Denison is also engaged in mine decommissioning and environmental services through its Closed Mines group (formerly Denison Environmental Services), which manages Denison’s Elliot Lake reclamation projects and provides post-closure mine care and maintenance services to a variety of industry and government clients.