home Equities T.DML announces decision to advance Wheeler River Project following positive PFS results

T.DML announces decision to advance Wheeler River Project following positive PFS results

Denison Mines Corp. (“Denison” or the “Company”) (DML: TSX, DNN: NYSE American) is pleased to report that the Company’s Board of Directors and the Wheeler River Joint Venture (“WRJV”) have approved the advancement of the Wheeler River project, following a detailed assessment of the strong economic results produced by the recently filed Pre-Feasibility Study (“PFS”) prepared for the project in accordance with NI 43-101 (see news release dated October 30, 2018). In support of the decision to advance the Wheeler River project, the WRJV has approved a $10.3 million budget for 2019 (100% basis), which is highlighted by plans to initiate the Environmental Assessment (“EA”) process as well as engineering studies and related programs required to advance the high-grade Phoenix deposit as an in-situ recovery (“ISR”) mining operation. Denison’s share of the 2019 budget for Wheeler River is $9.3 million, which reflects Denison’s 90% ownership interest in the project (see news release dated October 29, 2018).

Highlights from Wheeler River 2019 Budget

  • Initiation of Environmental Assessment process:  The submission of a Project Description (“PD”), to Federal and Provincial Regulatory Authorities is planned for early 2019, which is expected to initiate a multi-year EA, consultation, and permitting processes for the project.
  • Commencement of ISR wellfield tests: Field tests involving the drilling of ISR wells into the Phoenix deposit will be designed to assess permeability throughout the deposit by completing pump and other hydraulic tests within the orezone. The drilling of ISR wells will also allow for the collection of additional groundwater and ore samples, as well as provide assistance in refining the estimated cost of wellfield development.
  • Initiation of metallurgical ISR pilot plant testing:  Extensive laboratory studies replicating the ISR flowsheet are planned to test and optimize the mineral processing aspects of the Phoenix operation. Studies are expected to include the assessment of lixiviant chemistry and performance under a variety of permeability and grade conditions.
  • Discovery focused exploration program: Following years of delineation drilling for the Phoenix and Gryphon deposits, planned exploration activities in 2019 are designed to evaluate high priority regional target areas by focusing on initial testing of targets at the sub-Athabasca unconformity – which could lead to the discovery of further uranium deposits that may be amenable to ISR mining.

David Cates, President and CEO of Denison, commented “With the potential for a Phoenix ISR operation to have the industry’s lowest operating cost per pound of U3O8, as outlined in the Wheeler River PFS, the Board of Directors unanimously approved the advancement of the project and the 2019 budget.  The initiation of the EA process, as well as engineering and field studies designed to ultimately support a feasibility study, illustrates the Company’s commitment to achieving the project development timeline outlined in the PFS and claiming the ‘pole-position’ amongst undeveloped uranium projects in the Athabasca Basin region.  With plans for 2019 including a discovery-oriented exploration program and various engineering programs designed to de-risk the mine plan for the Phoenix ISR operation, we have the potential for several meaningful catalysts to emerge during the year.”

 

Wheeler River PFS: Phoenix ISR Highlights

The PFS considers the potential economic merit of co-developing the Phoenix and Gryphon deposits.  The high-grade Phoenix deposit is designed as an ISR mining operation, with associated processing to a finished product occurring at a plant to be built on site at Wheeler River.  Based on the PFS plan, first production from Phoenix is expected in 2024, with the development of the Gryphon deposit to follow with first production from Gryphon projected for 2030. The Phoenix operation is estimated to have a base case pre-tax Net Present Value (“NPV”) of $930.4 million (at 8% discount rate) representing the large majority of the project’s overall estimated pre-tax NPV(8%) of $1.31 billion – which includes the self-funding development of the Gryphon operation from cash-flows generated by the Phoenix operation.

The novel use of the ISR mining method at Phoenix pairs the world’s lowest cost uranium mining method with the world’s highest grade undeveloped uranium deposit (Phoenix) – in what could prove to be one of the world’s (1) lowest cost and (2) most environmentally friendly and responsible uranium mining operations.

  • Industry leading operating costs and comparatively low initial capex with ISR for Phoenix

Mine life

10 years (6.0 million lbs U3O8 per year on average)

Probable reserves(1)

59.7 million lbs U3O8 (141,000 tonnes at 19.1% U3O8)

Average cash operating costs

$4.33 (US$3.33) per lb U3O8

Initial capital costs

$322.5 million (100%)

Base case pre-tax IRR(2)

43.3%

Base case pre-tax NPV8%(2)

$930.4 million (100%)

Base case price assumption

UxC spot price(3) (from ~US$29 to US$45/lb U3O8)

Operating profit margin(4)

89.0% at US$29/lb U3O8

All-in cost(5)

$11.57 (US$8.90) per lb U3O8

(1)

For further details on mineral reserves refer to the NI 43-101 Technical Report on Wheeler River titled “Pre-feasibility Study for the
Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018 available on Denison’s website or 
on SEDAR at
www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml

(2)

NPV and IRR are calculated to the start of pre-production activities for the Phoenix operation in 2021;

(3)

Spot price forecast is based on “Composite Midpoint” scenario from UxC’s Q3’2018 Uranium Market Outlook (“UMO”) and is stated
in constant (not-inflated) dollars;

(4)

Operating profit margin is calculated as uranium revenue less operating costs, divided by uranium revenue.  Operating costs
exclude all royalties, surcharges and income taxes;

(5)

All-in cost is estimated on a pre-tax basis and includes all project operating costs and capital costs, divided by the estimated
number of pounds U3O8 to be produced

 

  • Environmental advantages of ISR mining at Phoenix – The Company’s evaluation of the ISR mining method for Phoenix has also identified several significant environmental and permitting advantages, namely the absence of tailings generation, the potential for no water discharge to surface water bodies, and the potential to use the existing Provincial power grid to operate on a near zero carbon emissions basis. In addition, the use of a freeze wall, to encapsulate the ore zone and contain the lixiviant used in an ISR operation, eliminates common environmental concerns associated with ISR mining and facilitates a controlled reclamation of the site. Taken together, the Phoenix operation has the potential to be one of the most environmentally friendly mining operations in the world. Owing largely to these benefits, consultation with federal and provincial representatives and stakeholder communities, to date, has been encouraging regarding the use of ISR mining.

Initiation of Environmental Assessment process

The PFS process identified the EA as a key element of the project’s critical path.  The PFS estimated a 3-4 year timeline to receive approvals under the existing regulations of the Canadian Environmental Assessment Act (“CEAA 2012”), allowing for construction to commence in 2022 with first production planned by 2024.

After careful consideration of the risks and opportunities associated with permitting and concurrent advancement of project engineering activities, the Company has decided to submit a PD and initiate the EA process in early 2019 for the Phoenix ISR operation, and to bring the Gryphon operation forward, at a later date, as required to achieve the PFS plan of Gryphon first production by 2030.  This is expected to simplify the EA and permitting process for the Phoenix operation and reduce the capital required to advance the project to a definitive development decision.

EA related expenditures planned for 2019 are estimated to be $2.5 million (100% basis) and, in addition to advancing the actual EA process, will include the continuation and expansion of the collection of certain baseline environmental data and the continuation of stakeholder consultation efforts.

Commencement of ISR wellfield tests

Additional field and laboratory work is needed to increase confidence and reduce risk in the ISR application at Phoenix. While preliminary field data supports the use of ISR, the ability to move fluids through the ore zone is an important technical risk that requires additional evaluation ahead of the initiation of a formal Feasibility Study (“FS”).

ISR field testing planned for 2019 is expected to include the installation of approximately 15 to 20 ISR wells into the Phoenix orebody, which is expected to provide a representative test of the various ore domains associated with Phoenix and the expected conditions in actual ISR operations. The field test is expected to have the following key objectives:

  • Confirm the ability to pump fluids through the various domains of the orebody and quantify volumes, pressures and other conditions required within the ore zones and surrounding host rock;
  • Confirm the ability, costs and schedule to drill larger diameter (8 inch) boreholes and set impermeable casings within the ground surrounding Phoenix;
  • Confirm baseline water conditions in, and surrounding, the deposit for the design of water treatment during operations, closure plans and the completion of expected environmental assessments;
  • Obtain additional representative ore samples from core drilling to facilitate extensive ISR metallurgical testing; and
  • Obtain surface geotechnical data of soils for foundation designs.

Expenditures related to the field testing planned for 2019 are estimated to be $2.4 million (100% basis).

Initiation of metallurgical ISR pilot plant testing 

The PFS results are based on metallurgical test work which was focused on proving the applicability of ISR mining (via column test) and leachability (via conventional leach tests) for the development of the Phoenix operation.  As the project advances through the EA process and towards the initiation of a FS, additional metallurgical test work is required to both test and optimize the metallurgical processing elements of the Phoenix operation.  A customized laboratory test program is expected to be developed to properly achieve the desired metallurgical test objectives – which are likely to include the following:

  • Assess the performance of different lixiviants in a variety of permeability and grade conditions;
  • Evaluate the potential for build-up of contaminants in the lixiviant;
  • Evaluate opportunities to recover rare earth metals as a by-product;
  • Increase confidence in the concentration of the lixiviant for the process plant design; and
  • Improve confidence in ground restoration abilities and cost estimates.

A laboratory scale pilot plant is planned to run over a one-year period, starting during the second half of 2019, with approximately $0.5 million (100% basis) budgeted for the setup and initial operation of the pilot plant in 2019.

Other project development activities

A further approximately $1.7 million (100% basis) is budgeted for project development / evaluation related activities in 2019, including the completion of certain third-party review studies, additional engineering trade-off studies related to the proposed Gryphon operation, program management costs, and operator fees to the WRJV.

The 2019 program is part of a multi-year project development plan that calls for the completion of a FS by the end of 2020 and receipt of final environmental and permitting approvals in 2021 or 2022 – which is expected to position Denison to make a definitive development decision on the project.  Future activities in 2020 and beyond may include:

  • Drilling of pilot / test freeze holes to increase confidence in costs associated with establishing the freeze wall surrounding the Phoenix deposit;
  • Completion of condemnation drilling and mineral resource updates at Phoenix to ensure potentially economic mineral resources are encapsulated within the freeze wall perimeter; and
  • Initiation of a formal FS in accordance with NI 43-101.

Discovery focused exploration program

The 2019 budget also calls for a $3.2 million (100% basis) discovery focused exploration program at Wheeler River. The program consists exclusively of diamond drilling, including approximately 13,500 metres in 23 planned drill holes.

Following the completion of the PFS and given the highly encouraging results from the proposed Phoenix ISR operation, the exploration drilling program will be focused on initial testing of targets at the sub-Athabasca unconformity, with the potential to discover additional ISR amenable uranium deposits.  Potential for basement hosted uranium mineralization will not be ignored where opportunities also exist to evaluate prospective basement targets.

High priority regional target areas planned for testing in 2019 include K West, M Zone, K South, Gryphon South, Q South (East), and O Zone, each of which is shown in Figure 2.

About Wheeler River

Wheeler River is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, in northern Saskatchewan – including combined Indicated Mineral Resources of 132.1 million pounds U3O8 at an average grade of 3.3% U3O8, plus combined Inferred Mineral Resources of 3.0 million pounds U3O8 at an average grade of 1.7% U3O8. The project is host to the high-grade Phoenix and Gryphon uranium deposits (discovered by Denison in 2008 and 2014, respectively), and is a joint venture between Denison (90% and operator) and JCU (Canada) Exploration Company Limited (10%). 

A PFS was completed, considering the potential economic merit of co-developing the high-grade Phoenix and Gryphon deposits, the results of which were announced on September 24, 2018. Taken together, the project is estimated to have mine production of 109.4 million pounds U3O8 over a 14-year mine life, with a base case pre-tax NPV of $1.31 billion (8% discount rate), Internal Rate of Return (“IRR”) of 38.7%, and initial pre-production capital expenditures of $322.5 million. The PFS is prepared on a project (100% ownership) and pre-tax basis, as each of the partners to the Wheeler River Joint Venture (“WRJV”) are subject to different tax and other obligations.

Further details regarding the Wheeler River project, including additional scientific and technical information relevant to the PFS, as well as after-tax results attributable to Denison’s ownership interest, are described in greater detail in the NI 43-101 Technical Report for the Wheeler River project titled “Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018with an effective date of September 24, 2018.  A copy of this report is available on Denison’s website and under its profile on SEDAR atwww.sedar.com and on EDGAR at www.sec.gov/edgar.shtml

About Denison

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northernSaskatchewan, Canada. In addition to its 90% owned Wheeler River project, which ranks as the largest undeveloped high-grade uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, Denison’s Athabasca Basin exploration portfolio consists of numerous projects covering approximately 320,000 hectares. Denison’s interests in the Athabasca Basin also include a 22.5% ownership interest in the McClean Lake joint venture (“MLJV”), which includes several uranium deposits and the McClean Lake uranium mill, which is currently processing ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest and Midwest A deposits, and a 65.92% interest in the J Zone and Huskie deposits on the Waterbury Lake property. Each of Midwest, Midwest A, J Zone and Huskie are located within 20 kilometres of the McClean Lake mill.

Denison is also engaged in mine decommissioning and environmental services through its Denison Environmental Services division and is the manager of Uranium Participation Corp., a publicly traded company which invests in uranium oxide and uranium hexafluoride.

Source: Denison Mines Corp.