T.DML Reports Decision to Increase Anticipated ISR Mining Head Grade at Phoenix by 50%

TORONTO, Aug. 4, 2021 /CNW/ – Denison Mines Corp. (“Denison” or the “Company”) (TSX: DML) (NYSE American: DNN) is pleased to report positive interim results from the ongoing metallurgical test program for the planned In-Situ Recovery (“ISR”) mining operation at the Phoenix uranium deposit (“Phoenix”), located on the Company’s 90% owned Wheeler River Uranium Project (“Wheeler River” or the “Project”). Test work completed to date, has consistently supported an ISR mining uranium head-grade for Phoenix in excess of the 10 grams / Litre (“g/L”) assumed in the Pre-Feasibility Study (“PFS”) completed for Wheeler River in 2018.  Accordingly, the Company has decided to adapt its plans for the remaining metallurgical test work, including the bench-scale tests of the unit operations of the proposed process plant, to reflect a 50% increase in the head-grade of uranium bearing solution (“UBS”) to be recovered from the well-field. View PDF version.

David Bronkhorst, Denison’s Vice President Operations, commented, “The metallurgical testing completed to date demonstrates that uranium can be consistently recovered from Phoenix cores at levels significantly higher than the 10 g/L extraction rate used in the PFS – giving rise to a decision to adapt future unit operation metallurgical tests to use a UBS head-grade of 15 g/L.  

A 50% increase in head-grade is expected to translate into meaningful optimization of previously estimated operating parameters and processing plant designs while maintaining the same level of annual uranium production – with the potential to reduce operating costs related to on-surface processing activities, and initial capital costs associated with the processing plant.”

Phoenix is expected to be mined in several phases, with Phase 1 estimated to contain 22.2 million pounds U3O8 (37,242 tonnes at 27.1% U3O8, above a cut-off grade of 0.8% U3O8) in Probable mineral reserves (see Press Release dated December 1, 2020). Accordingly, the sample selection for recent metallurgical test work has favored samples representative of the mineralization in Phase 1, to allow for a greater understanding of optimal leaching conditions required in the area where first production is expected.

Core Leach Test Results

Three core samples, representing the high-grade/low-clay characteristics of the majority of the mineralization in the Phase 1 mining area, have been tested to date, with results summarized below in Table 1 – showing steady-state and average UBS head grades significantly above the 10g/L level used in the PFS.

Table 1 – Summary Results from High-Grade/ Low clay Core Leach Tests

Sample #1

Sample #3A

Sample #3C

Sample diameter

6.1 cm

8.1 cm

7.8 cm

Sample length

19 cm

18 cm

7cm

Sample grade (U3O8)

70%

83%

83%

Clay Content

Low

Low

Low

UBS range in steady state (U)

13.5 g/L to 39.8 g/L

29g/L to 90g/L

14g/L to 74g/L

UBS average interval (U)

22g/L over 56 days

29.6 g/L over 85 days

31.1 g/L over 64 days

In addition to the high-grade/low clay characteristics of Phase 1, the Phoenix ISR operation is also expected to encounter comparatively rare and isolated areas with lower uranium grades and high clay content, which is expected to result in a limited number of zones of reduced permeability. In order to understand the ISR leach dynamics in these areas, test work was also initiated on samples presenting high clay characteristics (above 25% clay). Results obtained from these tests confirm that high clay content can impact the natural permeability of the ore body and lead to lower UBS head-grades.  Importantly, these tests also confirm that permeability enhancement techniques have the potential to normalize these areas and significantly improve UBS head-grade concentrations to levels that align with core leach tests carried out using samples with higher grades and lower clay content.

As outlined in Table 2, below, sample 2A failed to produce an acceptable “steady-state” UBS head grade. Sample 2B was taken from the same drill hole and presented similar mineralogical characteristics as Sample 2A; however, Sample 2B was modified to simulate the MaxPERF permeability enhancement tool.  As is evident from the achievement of a peak UBS head-grade of 76 g/L and an average UBS head-grade of 24.9 g/L obtained over 28 days of steady state, the preliminary leaching results from Sample 2B confirm both the utility of permeability enhancement in normalizing the natural permeability in high clay zones and the appropriateness of the decision to increase the overall UBS head-grade assumption for Phoenix.

Table 2 – Summary Results from medium Grade/ High clay Core Leach Tests

Sample #2A

Sample #2B(1)

Sample diameter

61mm

61mm

Sample length

12cm

10cm

Sample grade (U3O8)

28%

28%

Clay Content

High

High

Permeability Enhancement

No

Yes

UBS range in steady state (U)

N/a

5.8g/L to 76.0 g/L

UBS average interval (U)

3.8g/L over 1 day

24.9 g/L over 28 days

Notes:

(1) Core test is still in progress.  Results are as of August 3, 2021.

Column Leach Tests

Various column leach tests have recently been completed using core samples from Phoenix. The primary purpose of the column leach tests was to recover sufficient volumes of UBS to facilitate bench-scale tests of the unit operations outlined in the flowsheet for the Phoenix processing plant.  Over 900 litres of UBS were produced from 64 Kilograms (“kg”) of Phoenix core samples. Combined results from the four column leach tests are highly positive, with calculated UBS head-grade from the four columns averaging 19g/L, which further supports the decision to increase the overall UBS head-grade assumption for Phoenix.

While not the primary purpose of the column leach tests, average reagent addition rates from the column leach tests (1.3 kg acid / kg U3O8 and 1.2 kg oxidant / kg U3O8) have also provided useful information that is supportive of the values published in the PFS.

The laboratory work for the 2021 Metallurgical Program is being carried out at the Saskatchewan Research Council (“SRC”) Mineral Processing and Geoanalytical Laboratories, in Saskatoon, under the supervision of Mr. Chuck Edwards (P.Eng., FCIM).

About Phoenix Phase 1

Phase 1 of Phoenix is estimated to contain approximately 22.2 million pounds U3O8 (37,242 tonnes at 27.1% U3O8, above a cut-off grade of 0.8% U3O8) in Probable mineral reserves.  Based on current designs, the Company estimates approximately 6.6 million pounds U3O8 (7,717 tonnes at 39.2% U3O8, above a cut-off grade of 0.8% U3O8) in Probable mineral reserves are contained within the expected operating perimeter of the Test Pattern (see Figure 1). These estimates are derived as a direct subset of those reported in the Technical Report titled “Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018 with an effective date of September 24, 2018 (the “PFS Report”). The key assumptions, parameters and methods used to estimate the mineral reserves herein remain unchanged.

About Wheeler River

Wheeler River is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, in northern Saskatchewan – including combined Indicated Mineral Resources of 132.1 million pounds U3O8 (1,809,000 tonnes at an average grade of 3.3% U3O8), plus combined Inferred Mineral Resources of 3.0 million pounds U3O8 (82,000 tonnes at an average grade of 1.7% U3O8). The project is host to the high-grade Phoenix and Gryphon uranium deposits, discovered by Denison in 2008 and 2014, respectively, and is a joint venture between Denison (90% and operator) and JCU (Canada) Exploration Company Limited (10%).

A PFS was completed for Wheeler River in late 2018, considering the potential economic merit of developing the Phoenix deposit as an ISR operation and the Gryphon deposit as a conventional underground mining operation.  Taken together, the project is estimated to have mine production of 109.4 million pounds U3O8 over a 14-year mine life, with a base case pre-tax NPV of $1.31 billion (8% discount rate), Internal Rate of Return (“IRR”) of 38.7%, and initial pre-production capital expenditures of $322.5 million. The Phoenix ISR operation is estimated to have a stand-alone base case pre-tax NPV of $930.4 million (8% discount rate), IRR of 43.3%, initial pre-production capital expenditures of $322.5 million, and industry leading average operating costs of US$3.33/lb U3O8.  The PFS is prepared on a project (100% ownership) and pre-tax basis, as each of the partners to the Wheeler River Joint Venture are subject to different tax and other obligations. 

Further details regarding the PFS, including additional scientific and technical information, as well as after-tax results attributable to Denison’s ownership interest, are described in greater detail in the PFS Report.  A copy of the PFS report is available on Denison’s website and under its profile on SEDAR at www.sedar.comand on EDGAR at www.sec.gov/edgar.shtml

Denison suspended certain activities at Wheeler River during 2020, including the EA process, which is on the critical path to achieving the project development schedule outlined in the PFS.  While the EA process has resumed, the Company is not currently able to estimate the impact to the project development schedule outlined in the PFS, and users are cautioned against relying on the estimates provided therein regarding the start of pre-production activities in 2021 and first production in 2024.

About Denison

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. The Company has an effective 95% interest in its flagship Wheeler River Uranium Project, which is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region of northern Saskatchewan. Denison’s interests in Saskatchewan also include a 22.5% ownership interest in the McClean Lake joint venture (“MLJV”), which includes several uranium deposits and the McClean Lake uranium mill that is contracted to process the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and Midwest A deposits, and a 66.90% interest in the Tthe Heldeth Túé (“THT,” formerly J Zone) and Huskie deposits on the Waterbury Lake property. Each of Midwest Main, Midwest A, THT and Huskie are located within 20 kilometres of the McClean Lake mill. 

Through its 50% ownership of JCU (Canada) Exploration Company, Limited (“JCU”), Denison also holds interests in various uranium project joint ventures in Canada, including the Millennium project (JCU 30.099%), the Kiggavik project (JCU 33.8123%) and Christie Lake (JCU 34.4508%).

Denison is also engaged in mine decommissioning and environmental services through its Closed Mines group (formerly Denison Environmental Services), which manages Denison’s Elliot Lake reclamation projects and provides post-closure mine care and maintenance services to a variety of industry and government clients.

 

Source: Denison Mines